Progress made at port

Big build to boost Port of Auckland’s capacity takes major leap forward. 
Posted on 19 November, 2026
Progress made at port

Work on two major projects by Port of Auckland Ltd (POAL) is making strong progress with the first concrete deck pour completed at Bledisloe North Wharf and construction advancing on a new international cruise terminal. 

The first concrete pour, pictured, for the Bledisloe North’s deck covered 1,255sqm over a 13-hour continuous pour. It was the first of eight pours planned as it takes shape. The project is expected to reach halfway complete by Christmas. 

When finished, the wharf deck will have used about 2,410sqm of concrete, roughly enough to fill an Olympic-sized swimming pool. 

At the new cruise terminal, the framing, ceiling GIB, suspended ceiling and bulkhead ceiling installation have been completed. with ductwork and electrical and data work well progressed. 

POAL’s chief executive, Roger Gray, says the progress shows the two connected projects are moving closer to completion. “We’re getting on with our big build to grow cruises for the city and our team is making stunning progress after just one year of work. 

“The wharf deck is now being poured and the terminal is increasingly taking shape. There is still plenty of work ahead but these are big milestones.

“To maintain this progress, we have contracted our build partner for Bledisloe North, HEB, to roll straight onto delivery of the Fergusson North extension. Pre-work for this project is under way. 

“Together, the new wharf and terminal will give Auckland better infrastructure for larger cruise ships while also increasing the port’s capacity for roll-on, roll-off freight. 

“In addition to these projects, we’re extending Fergusson North and deepening the Rangitoto Channel through our existing consent package in 2027 to give us the facilities to handle larger container vessels.” 

POAL is investing more than $200 million in infrastructure to make the port capable of handling larger cruise ships, container vessels and more roll-on, roll-off vessels. Both projects are scheduled to officially open in March 2027.